New OSB Project In Alabama Gains Permitting

Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.

Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.

The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.

Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.

Some early work is being done at the site.

Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.

Latest News

Kadant Completes Key Knife Acquisition

Kadant Inc. has completed its previously announced acquisition of Key Knife, Inc. and some of its affiliates for approximately $156 million in cash, subject to certain customary adjustments. The acquisition was financed primarily through borrowings under Kadant’s revolving credit facility. Key Knife, a global supplier of engineered knife systems for custom chipping, planing, and flaking solutions for wood product industries, is headquartered in Tualatin, Ore. with…

The Luck Of The Irish

Article by Jessica Johnson, Senior Editor, Timber Processing, November 2023 – Earlier this fall, I had the privilege of heading to Ireland to see the sights, enjoy the scenes and. . .do a little work while I was at it. My second work trip to the Emerald Isle did not disappoint.

MiCROTEC Appoints New Corvallis CEO

MiCROTEC has announced the appointment of Ofer Heyman as its new Chief Executive Officer in Corvallis, Ore. Heyman brings a wealth of experience and a background in the industry, making him a valuable addition to the MiCROTEC team…

SPI Names Robert Hoover Vice President Of Resources

Sierra Pacific Industries (SPI) has named Robert Hoover Vice President of Resources, effective Jan. 1, 2024. He will work with SPI’s team of professionals who sustainably manage the company’s 2.4 million acres of timberlands and provide a steady log supply for the company’s sawmills. Hoover is assuming this role following the retirement of Dan Tomascheski at the end of the year…

Find Us On Social

Newsletter

The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.

 

Subscribe/Renew

Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative.