Alabama CLT Plant Is Nearly Operational
The first and biggest cross-laminated timber (CLT) manufacturing plant in the eastern U.S. is nearly fully operational, with 25 employees currently working a portion of the plant.
Florida-based International Beams (IB), a manufacturer of pre-fabricated i-joist beams, began converting a General Electric 227,000-square-foot into a highly-specialized CLT manufacturing facility last June. One portion of the main production has been installed – a wood grading component – in which technicians are currently learning the machines.
The second portion of the plant’s main production line is arriving from overseas during the next few weeks and should be installed by June, company owner Bruno Lebel told the Dothan Eagle. The plant should be 100 percent operational by September and employ 60 employees in total.
The plant is the first of its kind east of the Rocky Mountains, says Lebel, and will be the first in the world to produce both glue laminate wood and CLT. The $19.6 million investment will create 60 jobs at the plant right away, and create other jobs in local timber, sawmill, and trucking. Two hundred jobs will be created altogether.
International Beams says the CLT panels produced in Dothan will be sold mainly in the U.S. market. The company will use Southern pine lumber to construct the panels.
From Woodworking Network: woodworkingnetwork.com.
Latest News
U.S. Housing Starts Were Soft In January
U.S. housing starts began the new year ticking downward 4.5% in January from December to a seasonally adjusted rate of 1.309 million starts. Single-family starts came in at a rate of 841,000 in January, down 4.3%, while multi-family (five units or more) were at 457,000, down 5.4% from December…
Lumber Among Three Big Input Reductions
Softwood lumber is one of the three largest construction input cost reductions year-over-year from December 2021 to December 2022, according to a recent ConstructionDive market report. Citing Producer Price Index data from December 2022, the report noted that overall…
Biofuels Project Sinks
The Red Rock Biofuels project in southern Oregon appears headed for foreclosure according to notices published in the Lake County Examiner newspaper in late December after the company failed to make principal and interest payments on some $300 million in debt. The notice set a February 4 payment…
Find Us On Social
Newsletter
The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.
Subscribe/Renew
Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.